Manually updating work order operation start dates
Summary
How do you manully move a work order operation step to a future date without rescheduling (forward, back or mid? )Content
Hi
Have a work order with three operations, each require 8 est hrs to be simple.
- Strip and remove 8 hrs / fitter01
- Refurbish 8 hrs / fitter01
- Reinstall. 8 hrs / fitter01
Calendar resource avail hrs is 8 hrs, so this will take 3 days, however due to other work priorities, i want to manually set step 1 is monday, step 2 to friday, and step 3 ithe following wednesday.
Can't figure out how to update operaiton dates without kicking of the scheduling engine? Tried Mid Point, with first step completed, but it moved all the ops step to around friday (even completed one)