Allow Negative ETC on the project is not working
Summary
Allow Negative ETC on the project is not workingContent
Hi Team ,
Allow Negative ETC Calculation on the Forecast planning Options is enabled . But this process is not giving the expected Results.Please help in Resolution ,if im missing anything while doing the Process.
Process :
1. On a given Forecast Version , Task A on a project There is Some EAC = 5000 & ETC = 5000 EUR
2. Incurred Some Costs on Task A ( 5000 EUR) = Actual Costs
3. Post Updating the Forecast Version , i can see the Actual on the Version.
4. I have Incurred Some more Cost on the 1000 EUR , Now Making total Actual Costs = 6000 EUR
5. Now i Updated the Forecast version, Post updating the forecast ,it is observed that EAC got increased as Actual and ETC remains zero only instead of -ve amount (-1000 EUR)
Tagged:
0