Start or end of day when calculating suggested order/start/dock and due dates in supply planning
Summary
Start or end of day when calculating suggested order/start/dock and due dates in supply planningContent
We are using pre, post and proc lead times for make and buy items .In supply planning planned orders are created for the make and buy items and have these dates sugg start ,sugg order , sugg dock and sugg due dates generated on them When calculating these various suggested dates- do we say the order is due at the beginning or end of that date and does that differ between a PO(buy item) and WO(make item). Example if sugg due date is 23rd of jul - do we include 23rd of jul in the calculation (i.e. order is due at