Which Calendar is used for calculating processing/post processing and pre processing lead times for

edited Jun 7, 2021 9:58PM in Supply Chain Planning and Collaboration 7 comments

Summary

Which Calendar is used for calculating processing/post processing and pre processing lead times for make and buy parts

Content

Hello,

This is with regard to planned order dates 

Proc Lead Time= Sugg. Dock Date minus Sugg. Start Date

Pre Proc Lead Time = Sugg. Start Date minus Sugg. Order Date

Post Proc Lead Time = Sugg. Due Date minus Sugg. Dock Date

For buy part does supply planning assume a 7 day week calendar for calculating the processing lead time and the facility calendar for calculating the pre and post processing lead time?

And for a make part does it consider the  facility calendar for calculating the pre ,post and  processing lead times?