how to model run rate / through put in Supply Planning ?

edited Jul 30, 2021 4:27AM in Supply Chain Planning and Collaboration 1 comment

Content

Hello,

In EBS we had repetitive manufacturing where we could setup run rate or through-put.

How can we setup the same in Cloud? Example if we have through put of 10 units per hour..how to model this as capacity ?

Any thoughts? Thinking of setting a Resource called CAPACITY and assigning this to a Department with 10 units so that we can configure a constraint of 10 Units per hour or 80 Units per day assuming calendar of 8 hrs per day.

Thx