We enter sales orders for standard items(these are not ATO or PTO but just regular make items) but forecast at the component level. Example if we have a BOM for a regular make item as top level = TL having two components under it C1 and C2. We enter SO for TL and forecast for say C1. We would like SO demand from TL to explode to C1 and that should consume its forecast in supply planning. Is this possible to achieve using the forecast control attribute (consume/consume and derive) OR does this kind of functionality work only for configured items?