When does constrained supply planning overload and when does it use an alternate resource
Content
Hello,
Per Oracle documentation, the planning process applies capacity constraints in a specific order -
• Prebuild in earlier time buckets
• Offload to an alternate resource (if defined)
• Overload capacity (to meet demand due date)
We have run a few scenarios and see that even though there is availability in prior buckets, the alternate resource is being used and overloaded.
The expectation is that it should first pre-build, then use alternate and, if needed, overload primary. Has anyone faced a similar issue?