Expedite Date in Demand at risk exception and result of the accept action
Summary: What is Expedite Date in Demand at risk exception and which date - suggested due date or expedite date are we accepting when we click accept in the recommendation.
Content (required):In the demand at risk due to insufficient lead time as an example , there is a field called expedite date in the recommendations section . What does this date indicate? Is this the number of days the order must be further moved in from the suggested due date on the order? If yes then why does the plan not suggest the expedite date as the original suggested due date? Example we are seeing suggested due date on our WOs,Planned orders as 9/30 and the expedite date as 9/29 and expedite days as 1. Why does the plan not suggest
Tagged:
0