Supply Plan not considering Process MFG Work Definitions for Planning MAKE Supplies

Received Response
51
Views
9
Comments

Summary:

Supply Plan Engine not considering the Process MFG (Work Method) Work Definitions for planning MAKE supplies.

Content (required):

We have loaded Process MFG routings through FBDI to SCP Cloud successfully and available in ODS. We ran the supply plan (Both Constrained & Unconstrained) and reviewed the Planned order supply details. For the Planned Order Supplies, we could see Work Definition attribute is set to DEFAULT. Upon checking the Routings inside plan, it is not available. The same can be seen in Plan Inputs(ODS).

Supply Plan Engine does not consider the routings. Please let us know if there are any other setups we need to do take into consideration.