How do you configure Work Order Operations with a run-time without any resources?
Summary:
Resources are not being actively tracked. Work Orders have an average LT. However, when the WO is created/released, the LT is 0. Need to have the work order run time = Item LT.
Content (required):
I need a way to either pro-rate or average runtimes for Manufacturing Operations without resources being used.
Version (include the version you are using, if applicable):
21C
Code Snippet (add any code snippets that support your topic, if applicable):
Tagged: