Project / Task Actual Start & Finish Date is blank and greyed out
Summary:
I am trying to update the Project Task Actual Start and Finish Date but it is blank and greyed out. I set the baseline to project and tasks and published the progress but still those two fields are blank and greyed out. Is there any setting to make those fields editable. Please share if there is any documentation for this.
I have reviewed the below Oracle Support notes
Unable To Edit “Actual Start Date” And “Actual Finish Date” In Manage Financial ProjectPlan (Doc ID 2334290.1)
Actual Start And End Dates For Tasks (Doc ID 2194013.1)
Content (required):
Version (include the version you are using, if applicable):
Tagged: