Why two sales orders are considering by Planned Order for demands (with decimal value)
Summary:
There is a planned order in supply planning and when we checked the demand pegging for that planned order it is considering two sales orders with the pegged quantity of decimal value(Please refer the screenshot). Even both sales order suggested due date is different for this case.
We are expecting the system should consider only one sales order with the pegging qty of 400 (lot to lot Planned order).
Example:
Planned Order Qty - 432
Sales order 1 Pegged Qty - 399.58064
Sales order 2 Pegged Qty - 0.1613
Do we need to do any profile option setup for this issue?
Content (required):
Planned order is considering two sales order with decimal value instead of one sales order with Round off Quantity.
Tagged:
0