Hello all, I have a question please for the partners/customer who have applied the supply planning.
Summary:
The Fixed days supply isn't working in constrained process-based work definitions. the quantities are gathered in one order but with the start date is the same as the due date. and we have to do so because the planned orders quantities are the same as the work definition quantity (Lead time lot size quantity), and I want the planned orders to be gathered in one order with the manufacturing lead time honored.
Content (required):
Version (include the version you are using, if applicable):
Code Snippet (add any code snippets that support your topic, if applicable):
Tagged: