How to enable new reporting resource breakdown structure for project assignment?
Summary:
How is a new reporting RBS made available to add to a project? I'm missing something.
Content (required): I am attempting to use the reporting RBS in a project allocation rule. I have created a new reporting RBS that is enabled for allocations (cannot edit the planning RBS as per MOS note 2593816.1) and frozen the version and it is available to be added to an allocation rule. Upon allocation generation though I get an error - The allocation wasn't generated because the resource breakdown structure isn't assigned to the source project - but the new RBS is unavailable to be added to the project (or template), the lov is empty.