I have a Project Task that is not available in Expense entry. I can select the project but the Task LOV is empty, following has been verified:
- Transaction Controls do not exist
- Expense date within project task planned/transaction dates
- Project Dates are in line too and so is status, we are able to select the project
- Task is chargeable
- Person is in the same BU as the project, so no cross charging in play
- the Expenditure type is mapped in the expense template setup, but that would be an issue before even getting to the Project.
- User is able to select the task in time and labor