Mismatch between the dates entered on an Agreement (BPA) and the BPA Print PDF
Summary:
For the BPA, we are entering the Start Date and End Date on the header and the Expiration Date at the Line level. However after approval when we open the BPA Print PDF using the 'View PDF' option, all the dates on the PDF are displayed 1 day before the value entered on the BPA. Please see attached screenshots with the details highlighted.
Ex: Start Date on BPA = 12-Dec-2022, but on the BPA print PDF = 11-dec-2022, similarly for other dates also
Please let us know if this is an expected functionality or is there any configuration available to control the dates, or is this a bug, please help.
Tagged:
0