Unable to generate burdened costs
Summary:
No burden cost multipliers are being applied on raw costs
Content (required):
I am trying to setup burden multipliers for project costs coming from timecards and misc project costs, however nothing is being applied on the the expenditure items. I am wondering is there is a setup that I may be missing?
Here are the configs done so far:
Raw costs and burdened costs are the same on all transactions tested so far. Same thing when I test the schedule using Test Burden Cost Calculations
Thanks for any input on this
Version (include the version you are using, if applicable):
Tagged:
0