Help to enable Budgetary Control with Project

Summary: I am not able to enable the budgetary control. When I create a requisition or order, the error occurs."The project is enabled for budgetary control but there is no control budget. Create a control budget by setting the budget to baseline and validate the transaction. "

Is another configuration required?


MY SETUP

========

1) Setup > "Budgetary Control Management and Charge Accounting" > only for projects > done


2) Setup > Project Financial Management > PROJECT CONTROL > Manage Financial PLan Type

a) I Enable budgetary controls

b) Tab : Budgetary Control Settings > Control Budget x Control Level

> Project and Top Resource with Advisory


3) Create Project > My Project > Open project > Manage Financial Project Settings