Is forward scheduling possible for B2B Work Orders?

Summary:


Content (required):

We observed that the B2B Work Orders are always backward scheduled. In other words, the Work Order Start Date is calculated based on Sales Order Requested Delivery Date. Is it possible to forward the schedule for scenario where the start date is the past?

Eg. SO Requested Delivery Date: 19-Mar

Below is how the dates are calculated.

WO Start Date: 27-Feb

WO End Date: 19-Mar

Expectation:

WO Start Date: Today

WO End Date: 8-Apr

Version (include the version you are using, if applicable):

23A

Code Snippet (add any code snippets that support your topic, if applicable):