Hi All,

We are rolling out Finance and Procurement across the globe with a phased Go-Live approach. So, we plan to go live in OCT-18 and our UAT is in SEP-18. The problem is my UAT environment will be in R13 18A (sep). When I go-live, my PROD POD is scheduled for 18B. Having business signoff on 18A and going live with 18B is not advisable. So, how do we resolve this?. We plan to have a quarterly releases and are stuck with this issue.

Thanks, Bala.