Need details on project costing without stripping inventory by projects
Summary:
Understand that we could enable inventory tracking by project at inventory organization level. Is it feasible to not enable this option to prevent stripping of inventory project but have sales order issue/picks using PJC project attributes instead of INV project attributes?
Content (required):
The organization is using projects for billing and revenue for part of the business. They do not stripe or segregate inventory by project or task. They have projects that are enabled on cost collection so they could use Oracle PPM to collect costs. The requirement is continue reserving the material by the demand e.g. sales order but collect cost for these sales into Oracle PPM with project clearing from costing. Is that feasible? I know there are PJC project attributes and INV project attributes. I do understand that INV project tracking attributes are for warehouse segregation while PJC are costing