Background processes to be scheduled
Summary:
We are currently implementing on 23A,and have enabled Redwood UI for both Learners and Managers.
We have scheduled the processes as per the background processes in the implementation guide, and added the 2 new Redwood manager UI processes, please can someone confirm that this is the correct order.
1. Process Learning Records
2. Process User Access
3. Process Access Control Lists for Learning Items for OSCS
4. Process Learning Recommendations
5. Process Learning Alerts
6. Update Assignment Status on Date-Driven Activities
7. Change the Status of Offering Assignments with Any Pre-Active Status to Delete
8. Compute Users ACL by Events (for Redwood Manager)
9. Compute Users ACL (for Redwood Manager)
Tagged: