Keep a reportable reference to original planned finished date
Is there an out of the box way / field to keep track of the original planned finish date of a project.
PFM only
Users will enter a Project Finish Date to cascade to tasks when setting up project initially, i.e. June 1, 2023
If the project needs to be moved forward due to changes, then users will update the Project Finish Date and Cascade down to Tasks, i.e June 30, 2023
The reporting requirement is to be able to report on both the June 1, 2023 date as Original Finish Date vs June 30, 2023 as Actual Finish Date.