Hi is there any method to update the Project setting: "Automatically roll up task planned dates" from Y to N for multiple projects?

Content (required):

We have updated the template so new projects have the relevant setting but we have thousands with the incorrect setting. Is there any means to update this via FBDI or API etc to update them in bulk? I cant find one in the library.

Example Navigation: Fusion - Projects - Projects Financial Management - Search Project - Tasks - Manage Financial Project Settings - Planning Tab - Edit - Task Settings Tab - Uncheck Automatically roll up task planned dates - Save.