I wanted to share some insight into how a budgetary controlled purchase requisition works for order processing. This was a recent customer question (and I have seen similar ones before) and thought it might be good to remind customers of behavior.
Specific Scenario:
The purchase requisition contains a line for quantity 50 Units
This requisition is processed into a purchase order
The order is processed only for quantity 30 Units
Question:
What happens to the remaining quantity 20 Units on the purchase requisition
Expected Behavior:
When a purchase order is created from a requisition line, in the above scenario, two things happen: