Supplies/Demands SO Line Material Availability Date is later than its supplies max pegged date

Summary:

In Supply Planning "Supplies and Demands" table the engine is generating the "Material Availability Date" at a much later date compared to the pegged demands' Max "Suggested Due Date" for a specific Sales Order Line Demand.

How is the "Material Availability Date" and the "Planned Arrival Date" being calculated?

Content (required):

Sample:

Today's date = 2023-JUN-06

Demand:

Org: CONCORD/ Item: 1233/Order Type: Sales order/ SO# 123456 /Line#: 1/ Order Qty: 100/ Request Date: 2023-JUN-05

Pegged Supplies:

Org: CONCORD/Item: 1233/Order Type: On hand/ Subinventory: Storage/ Order Qty: 50/ Suggested Due Date: 2023-JUN-06

Org: CONCORD/Item: 1233/Order Type: On hand/ Subinventory: Storage2/ Order Qty: 60/ Suggested Due Date: 2023-JUN-06