How the transfer order requested delivery date is sent to Supply Planning?

Summary:

Trying to figure out what dates are related between transfer orders and supply plan

Content (required):

We have some troubles sometimes to figure out which date is what.

Transfer orders are created from Supply Planning planned orders.

There is a requested delivery date that is populated on June 9th.

When looking at the plan from the source organization perspective, the suggested ship date is the same than the requested delivery date of the TO, June 9th, and not the same than the scheduled ship date of the TO which June 7th.

Should an exception be triggered because we are late regarding the dates on the transfer order?