Cost accounting distribution balance

Accepted answer
61
Views
5
Comments
edited Jun 21, 2023 2:38PM in Costing 5 comments

Summary:

PO is delivered into work order and closed for receiving but its coming as balance in CAD report

Content (required):

PO is delivered into work order and closed for receiving but its coming as balance in CAD report. What could be the reasons? Whats the fix. Work order PO ordered and received quantities are matching

Version (include the version you are using, if applicable):