Generate Burden Costs - Expenditure Item Through Date parameter does not increment
Summary:
Generate Burden Costs - Expenditure Item Through Date does not increment
Content (required):
When a system I support was implemented, the "Generate Burden Costs" job was set to run daily with the "Expenditure Item Through Date" parameter set to 20th December 2022.
The job runs each day at 10pm.
However, the value of the "Expenditure Item Through Date" parameter has remained set to 20th December 2022 for the duration of the schedule.
Is there any way we can get the Through Date to increment by 1 day each time the job runs?
Or are the only options to set the Through Date to a long time in the future instead, or, to manually run it when required using today's date as the "Expenditure Item Through Date" parameter?