PO data not interfaced to Landed cost management
Summary: PO data not interfaced to Landed cost management. Unable to find the PO in landed cost management
Content (required): A PO is created and approved. Landed Cost Process - Prepare material PO date is executed to interface this PO to landed cost module.
The Landed cost processor completed successfully but PO is not available in landed cost management.
Please let me know what could be causing the issue as we tried to find any possible cause but unable to. Appreciate any help on this issue.
Version (include the version you are using, if applicable):
Code Snippet (add any code snippets that support your topic, if applicable):
Tagged:
0