Alternatie item/Component in Supply Planning
Hello,
I have an issue, and I want to make sure if it is possible or not.
I have a factory org (Org: Fac) and a Warehouse or (Org: WH).
I am having a raw material X, which has an alternate/substitute called X1 which I defined as a substitute.
In org Fac, using the planning module, when X is not available, then the plan recommends Item X1 in the FAC org.
But if X and X1 not available in the FAC org, then the system recommends IR from WH, but then if X is not available in WH org then the system recommends to create PR regardless that X1 is existing in the WH Org.