Why is a New Base Contract created for a Negotiation Amendment?
Summary:
A new Base Contract is created when you Amend a Negotiation.
Why? This does not seem correct.
Content (required):
When you create an initial Negotiation, select the Contract Terms Tab, select Create Contract, a Base Contract is generated for the Negotiation.
When you Amend the Negotiation, a brand new Base Contract gets generated.
Why does this occur if we are only adding an additional Line for example?
This does not seem correct to me.
Version (include the version you are using, if applicable): 23C
Code Snippet (add any code snippets that support your topic, if applicable):
0