How to handle work schedule and partial day logic in duration formula?

Received Response
21
Views
5
Comments

Summary: On the basis of requirement for Vacation - PL absence type, we are submitting leave for more than 1 day. But from the balance system is only deducting 1 day of leave which is the start date of our leave.


Content (required):


Version (include the version you are using, if applicable):


Code Snippet (add any code snippets that support your topic, if applicable):

/******************************************************************************

FORMULA NAME: UL_PL_VACATION_DURATION


FORMULA TYPE: Global Absence Type Duration


DEFAULT FOR IV_START_DATE IS '4712/12/31 00:00:00' (date)

DEFAULT FOR IV_END_DATE IS '4712/12/31 00:00:00' (date)

DEFAULT FOR IV_START_TIME IS '00:00'