Is there task Capitalizable Indicator attribute on MS Project Integration (Project Management)?
Summary:
I don't see a capitalizable indicator attribute on MS Project.
Content (required):
I need to create capital projects with financial and non-financial Tasks from Microsoft Projects and some financial tasks need to be created as non capitalizable.
The MS Project integration was downloaded from Project Management (not Project Financial Management) because there are non financial tasks.
I didn't find a capitalizable indicator attribute to set some tasks as non capitalizable. There are chargeable and Billable indicators, but not capitalizable indicator.
Is there capitalizable indicator attribute on MS Project?
If no, is it possible to create a new attribute mapping on MS Project integration to map that?