Does cost roll up take into account the number of Resource Units Assigned
Summary:
When calculating Direct Labor Cost during the cost roll process does it take into account the number or Resource Units Assigned to that Work Center? I have an Operation that required 2 resources at $50 rate. When I do cost roll, all I am seeing is the Labor Cost being calculated based on the $50 rate multiplied by the Usage Rate. (Operation Basis = Variable)
Example:
(Resource Rate = $50) x (Usage Rate = 1) = $50 Direct Labor
What I would expect is :
((Units Assigned = 2 )X(Resource Rate = $50)) x (Usage Rate = 1) = $100 Direct Labor