Basis Type Fixed Vs Variable on the Operation Resource in Work Definition
Summary:
Basis Type Fixed Vs Variable on the Operation Resource in Work Definition
Content (please ensure you mask any confidential information):
We have a Basis column on the Operation Resource. The value of the Basis field could be Fixed or Variable.
We are observing the following behavior for this field.
1. If the value is Fixed, system does not validate the lead times and per hour processing capacity while creating Work Orders after releasing planned orders.
2. If the value is Variable, System validates the lead times and per hour capacity while creating Work Orders after releasing planned orders.
Can someone confirm if the above understanding is correct?