Receipt cost not getting import to project
Summary:
We are using project driven supply chain feature where the follow step have followed to import the receipt cost to project.
- Project related Purchase order with destination type 'Inventory' is created and once approved.
- Ran the Update Project performance process
- Ran Import commitment (PO related cost is available as commitment)
- Receipt was created.
- ran the transfer receiving cost to costing
- ran create receipt distribution process (able to review receipt details)
- Ran create accounting process in final mode.
- Ran Import cost process (Cost is not getting imported to project)
- however Ran the Update Project performance process and Ran Import commitment (PO related cost is reduced to the extend receipt)