Physical Percent Complete(%) calculations don't match.
Summary:
Physical Percent Complete(%) calculations don't match.
I entered 1,000,000 as Planned Cost in one task and activate Baseline Planned.
Next I import 500,000 cost that is Planned Resources from AP.
Then I generated Burden Cost, 5 Burden Costs of 10,000 each generated .
Actual Cost is 550,000 and Planned Cost is 1,000,000, so it is supposed to be 55% but it turned out to be 52.38..%.
Why wasn't it 55%? How was it calculate?
Please let me know.
Thanks,
Mayuko