Calculate Min-Max Parameters is taking incorrect lead-time
Hi there.
We are running the 'Calculate Min-Max Parameters' scheduled process for a min-max policy defined at organization level (no subinventory involved).
In the log of the process we see that it's considering 1 day for the lead time...
...although the items (not only one item), that are purchased items (not manufactured--->no work definition, no lead time calculation...) are defined at organization level like that:
So, the question is why the process takes 1 day as lead time, when it should be 0.
Another clue: we have checked that if we define, for instance, 2 days in the processing days field, then it takes 2 days, correctly. But we don't understand why it takes 1 day "by default" if the item has these fields empty...
0