Unable to recognize rev using this formula: Rev = Contract Value* Actual Cost/Approved EAC

edited Dec 14, 2023 6:33PM in Project Management 16 comments

Summary:


Content (please ensure you mask any confidential information):

We need to be able to recognize revenue on projects based on the following formula:

Revenue= Contract Value* Actual Cost/Approved EAC

When we use the Percent Spent revenue method classification, it calculates revenue based on following formula: Revenue= Contract Value* Actual Cost/Approved Cost Budget

BUT, we need the denominator in this formula to be APPROVED EAC rather than the cost budget.

Version (include the version you are using, if applicable):


Code Snippet (add any code snippets that support your topic, if applicable):

Howdy, Stranger!

Log In

To view full details, sign in.

Register

Don't have an account? Click here to get started!