Unable to recognize rev using this formula: Rev = Contract Value* Actual Cost/Approved EAC
Summary:
Content (please ensure you mask any confidential information):
We need to be able to recognize revenue on projects based on the following formula:
Revenue= Contract Value* Actual Cost/Approved EAC
When we use the Percent Spent revenue method classification, it calculates revenue based on following formula: Revenue= Contract Value* Actual Cost/Approved Cost Budget
BUT, we need the denominator in this formula to be APPROVED EAC rather than the cost budget.
Version (include the version you are using, if applicable):
Code Snippet (add any code snippets that support your topic, if applicable):