Configure Project Accounting Business Function setup
Summary:
We have a requirement that Project and Task Owning Orgs need to be associated to the subledger business units to restrict which organizations can incur costs on a project - this will prevent users from selecting an incorrect org which causing Create Accounting errors.
As per the above business request, we are trying to enable "Use different details for project expenditure organization" option in Configure Project Accounting Business Function setup.
In existing design, we are using the same details for both Project task owning org and project expenditure org. Kindly advise if there is any potential impact on subledgers or existing functionalities/reports.