Planned Value and schedule performance Index calculation
Summary:
the SPI = EV / PV ,
As per the image below the PV is supposed to be distributed evenly across the baselined dates .
when using the capability to distribute the planned amount -edit period amount- in the financial plan I have distributed amounts manually - not evenly - so the budget to date or the PV is supposed to be calculated as per the specified distribution not evenly , as this will provide inaccurate data
My question is related to the possibility to use the Planned Values that I have specified in the Project Plan and the Budget to get the PV as per my plan