Issue in consolidation of Inbound shipments from Supplier to Cross Dock
Hi Team,
We have a requirement where shipments should be going via cross dock in the first leg and then from cross dock to Final destination. Ideally business expectation is that the orders in the first Leg i.e., until cross dock should be consolidated into single shipment. But we are getting multiple shipments when planned the orders using Bulk Plan.
We are using Network Routing in the Itinerary Leg. There are no issues with respect to Equipment weight and volumes as OTM is allowing us to Manual Merge the First leg shipments without any issues. But it fails to consolidate the orders when planned via Bulk Plan. Kindly let us know if there is any other configuration needed to achieve the same.