Unable to capture progress when project budget created manually along with forecast.
Summary:
Unable to capture progress when project budget created manually along with forecast
Content (please ensure you mask any confidential information):
Hello Team,
In Track Project Progress when calculation is based on cost(derive physcial % complete) and remaining plan(ETC Method calcualtion) , system is calcuates 100% and mark task as actual finish date whereas the costs which has been captured against the project is not even 10% of budget value of that task and 1% of project budget.
And even if we continue capturing costs on project and capture progress it remains 100% and actual % doesnt get rolled up to project level neither system calculates it.