Manage Project Costs - Export to Excel is submitting an ESS process "Export Data to Excel"

edited Feb 21, 2024 3:49PM in Project Management 19 comments

Summary:


Content (please ensure you mask any confidential information):

After upgrading to 24A,

Issue – 1 :- PFM - >Manage Project Costs - >Export to Excel icon is not showing, Page need to be refreshed to show the icon. (refer below screenshot)

Issue – 2 :- PFM - >Manage Project Costs - >Export to Excel is submitting an ESS process "Export Data to Excel", instead of downloading the excel sheet.

Is it the new functionality in 24A for PJC?

Note - PFM ->Manage Unprocessed Costs - >Export to Excel is working fine and downloading the excel sheet.

Version (include the version you are using, if applicable):