How ETC is calculated in project progress area

The ETC has two methods , Manual or Remaining Plan

When I select Remaining Plan at lowest task level I get it available for manual entry at the resource , meanwhile the calculations aren't clear for me , as ETC is supposed to be as the equation ETC = Baselined Plan - Actual costs ?