Budget not rereleased for cancelled PO and new PO cannot be entered budget error
Summary:
Budget not rereleased for cancelled PO and new PO cannot be entered budget error
Content (please ensure you mask any confidential information):
A PO was created against a PR and recieved and invoiced. The budget was reserved ad liquidated accordingly.
The invoice , GRN and PO was cancelled .
The amount cancelled is not shown in the review budget as avaialable funds.