No periods were identified for loading data into table 'TDATASEG' when running integration
Summary:
Hello everyone,
I need to get budget data from ERP to EPBCS.
But unfortunately, the integration run failed in Dec-2024 with the log:
"RuntimeError: No periods were identified for loading data into table 'TDATASEG'."
I checked the period mapping in EPBCS data integration and saw the global mapping is enough:
And there is no period mapping for source mapping:
And there is no period mapping for application mapping:
I tried to re-run this integration with a period Dec-2023, and it ran successfully.
I dont know why period Dec-2024 run failed although it is the same as Dec-2023?
Version (include the version you are using, if applicable):
Tagged: