RMCS will consider the revised currency rate if it gets updated in the future?
Summary:
Hi Team
Could you please provide your answer for below question and do the needful.
Eg: We have one contract which is in EUR currency and SSP is in USD currency and OSS sent one new future line to the RMCS and the line successfully appended to the contract, but it gets stuck with reference currency error.
- I have one obligation line which is start in the future (Eg: 01-May-2024) and sent this line to RMCS today from OSS. As per immaterial change this date 01-May-2024 is my contract modification date.
- It stuck with Reference currency error since no rate available in GL rates on 01-May-2024.