New resources added to RBS not getting reflected on project enabled for budgetary control
Summary:
If a project is enabled for budgetary control, the new resources added to RBS are not available to be selected when adding planning resources to project budget. This is happening even after refresh RBS and update mapping has been completed after adding new resources to RBS and a new project is being created.
Content (please ensure you mask any confidential information): We have the following settings
RBS - Allow changes at project level enabled
Budgetary control enabled for project and financial plan type
Steps
Added new planning resources to RBS
Ran refresh RBS and update mapping
Created new project and trying to create budget by adding the planning resources to the budget - The newly added resources are not available.